Legislation Details

File #: 26-2946    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 4/30/2026 In control: Commissioners Court
On agenda: 5/14/2026 Final action: 5/14/2026
Title: Request for approval of an agreement with Cascade Civil Services, LLC, in the amount of $1,000,000, to provide preliminary engineering, design, bidding, and construction phase engineering services in support of Telge Stormwater Detention Basin at Pleasant Grove Road (Cypress Creek Watershed, Bond ID Z-04, Project ID K500-28-00-E001, Agreement No. 2024-64, Precinct 3, MWBE Contracted Goal: 19.60%).
Attachments: 1. 051426 AGMT CASCADE 2024-64 PCT 3 backup.pdf
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): K500-28-00-E001
Vendor/Entity Legal Name (if applicable): Cascade Civil Services, LLC

MWBE Contracted Goal (if applicable): 19.60%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an agreement with Cascade Civil Services, LLC, in the amount of $1,000,000, to provide preliminary engineering, design, bidding, and construction phase engineering services in support of Telge Stormwater Detention Basin at Pleasant Grove Road (Cypress Creek Watershed, Bond ID Z-04, Project ID K500-28-00-E001, Agreement No. 2024-64, Precinct 3, MWBE Contracted Goal: 19.60%).
end

Background and Discussion:
The limits are marked along HCFCD Unit K100-00-00 and located at the Cypress Creek Watershed along the channel K100-00-00, near the intersection of Whispering Valley Dr and Telge Road. This Agreement will provide preliminary engineering. This project has been identified in the Cypress Creek Implementation Plan, and the PER associated with this project will determine the benefits and geometry for the proposed stormwater detention basin. This project occurs in the 2nd quartile under the 2022 Prioritization Framework approved by Commissioners Court.

Expected Impact:
The project seeks to reduce flood risks and strengthen resiliency in the Cypress Creek watershed by helping to mitigate overland sheet flow, overbank flooding, insufficient drainage capacity, overflows from neighboring catchments, an...

Click here for full text