Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom Ramsey, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 22/0019, UPIN 22103MF2E401
Vendor/Entity Legal Name (if applicable): GLM Contracting, Inc.
MWBE Contracted Goal (if applicable): 19%
MWBE Current Participation (if applicable): 32.86%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with GLM Contracting, Inc., in connection with On-Call - Construction - General Civil, Precinct 3 - 2021, with no change in the amount, Job No. 22/0019-2, UPIN 22103MF2E401, Precinct 3, MWBE Contracted Goal: 19%, MWBE Current Participation: 32.86%.
end
Background and Discussion:
Project includes general civil services including concrete and asphaltic repairs at various locations throughout Precinct 3. The change in contract is to include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes. The Precinct has requested for new bid items to be added.
Change includes adding the following bid Items:
1- Item 110 - Oversize Tree Removal ($2,100/EA - PCO # 77)
2- Item 105 - Oversized Tree Trunk ($1,000/EA - PCO # 79)
3- Item 104 - Secure Fence ($100/EA - PCO # 86)
4- Item 118 - Remove Utility Poe ($100/EA - PCO # 87)
5- Item 119 - Demo Underground Junction Box ($100/EA - PCO # 88)
All missing in the current bid.
The new bid item is only to establish the unit price and there is no change to the contract amount.
Expected Impact:
Change allows C...