Legislation Details

File #: 26-2813    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 4/27/2026 In control: Commissioners Court
On agenda: 5/14/2026 Final action: 5/14/2026
Title: Request for approval to execute an agreement with AKV Consultants, LLC in the amount of $390,158.00 for Professional Engineering Services in connection with Bridge Repair - East Hardy Road over Greens Bayou, UPIN 26101MF3YT01, Precinct 1, MWBE Contracted Goal: 19.68%.
Attachments: 1. Award-26101MF3YT01-BridgeRepairEastHardyRoad- AKV Consultants LLC-P1-04-16.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 26101MF3YT01
Vendor/Entity Legal Name (if applicable): AKV Consultants, LLC

MWBE Contracted Goal (if applicable): 19.68%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with AKV Consultants, LLC in the amount of $390,158.00 for Professional Engineering Services in connection with Bridge Repair - East Hardy Road over Greens Bayou, UPIN 26101MF3YT01, Precinct 1, MWBE Contracted Goal: 19.68%.
end

Background and Discussion:
Bridge repair project is needed to address structural deficiencies identified in the Bridge Inventory, Inspection, and Appraisal Program (BRINSAP). Project consists of Northbound and Southbound East Hardy Road Bridges at P100-00-00. Consultant to design bridge repair improvements based on BRINSAP report.

Expected Impact:
This action will allow AKV Consultants LLC to provide professional engineering services for the project.


Alternative Options:
No alternative options. If not approved, project will be delayed or cancelled.




County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (G...

Click here for full text