File #: 26-2797    Version: 1 Name:
Type: Utility Agreement Status: Passed
File created: 4/23/2026 In control: Commissioners Court
On agenda: 5/14/2026 Final action: 5/14/2026
Title: Request for approval to execute an Underground Facilities Extension Agreement and Supplemental Terms & Conditions package with CenterPoint Energy, LLC, in the amount of $128,800.00 for the cost associated to provide new underground electrical service for the new HCSO Complex at 5910 Navigation Blvd., Houston, Texas 77011, including all deposit/fees for utility services, UPIN 21201MF22Z01, Precinct 2.
Attachments: 1. 26-2797-UA-21201MF22Z01-5910 Navigation-HCSO Complex-Centerpoint Energy-P2
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Utility Agreement

Project ID (if applicable): 21201MF22Z01
Vendor/Entity Legal Name (if applicable): CenterPoint Energy

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: 0% - Specialized, Technical, or Unique in Nature

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an Underground Facilities Extension Agreement and Supplemental Terms & Conditions package with CenterPoint Energy, LLC, in the amount of $128,800.00 for the cost associated to provide new underground electrical service for the new HCSO Complex at 5910 Navigation Blvd., Houston, Texas 77011, including all deposit/fees for utility services, UPIN 21201MF22Z01, Precinct 2.
end

Background and Discussion: CenterPoint Energy LLC requires a signed Facilities Extension Agreement and Terms & Conditions package to provide two points of underground electrical service for the new HCSO Complex. The requested service will provide the complex with the required infrastructure and service needs to the facilities.

Expected Impact: The agreements and payment are required for the project to move forward and comply with the project's electrical utility needs.

Alternative Options: There are no alternative options as CenterPoint is the only entity we can work with for matters regarding electrical infrastructure and service.

County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Econo...