Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0075, UPIN 15104MF0DN02
Vendor/Entity Legal Name (if applicable): Brice Construction and Design, LLC
MWBE Contracted Goal (if applicable): 30%
MWBE Current Participation (if applicable): 99.23%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Brice Construction and Design, LLC, in connection with final construction of Telge Road Segment 4 - from 1,650-ft North of Louetta Road to 1,780-ft North of Telge Ranch Road - 2014, adding 5 calendar days, with an addition in the amount of $93,658.49, Job No. 24/0075-4, UPIN 15104MF0DN02, Precinct 3, MWBE Contracted Goal: 30%, MWBE Current Participation: 99.23%.
end
Background and Discussion:
Project included the reconstruction of Upgrade Telge Road from 1,650-ft North of Louetta Rd to 1,780-ft North of Telge Ranch Road. Reconstruction includes an upgrade of the roadway from a two-lane asphalt road with open ditches to a 4-lane concrete curb and gutter boulevard with a 32' raised median. The contract adjustments are necessary to properly compensate the contractor for additional work, including improving pavement ride quality to ensure safer and smoother road conditions, addressing delays caused by required coordination and conflict resolution with existing utilities, and performing additional concrete removal and labor after encountering an unforeseen conflict with the buried foundation of the existing brick wall during slope-pa...