Title: Request for approval to execute an agreement with HDR Engineering, Inc. in the amount of $1,160,565.81 for Professional Engineering and related services in connection with Design Phase Services of Holderrieth Rd Segment 4 - from Sir Alex Dr to SH 99 - 2025, UPIN 25103MF3VP01, Precinct 3, MWBE Contracted Goal 2.77%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN - 25103MF3VP01
Vendor/Entity Legal Name (if applicable): HDR Engineering, Inc.

MWBE Contracted Goal (if applicable): 2.77%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with HDR Engineering, Inc. in the amount of $1,160,565.81 for Professional Engineering and related services in connection with Design Phase Services of Holderrieth Rd Segment 4 - from Sir Alex Dr to SH 99 - 2025, UPIN 25103MF3VP01, Precinct 3, MWBE Contracted Goal 2.77%.
end

Background and Discussion:
Precinct 3 is requesting that the Office of the County Engineer enter into an agreement for professional engineering services to provide design-phase services for the subject roadway project. The project consists of the design of Holderrieth Road Segment 4, from Sir Alex Drive to State Highway 99. The recommended solution includes a four-lane concrete curb-and-gutter boulevard with 32-foot raised medians within 100-foot right-of-way. The scope of work includes the design of the roadway, storm sewer system, traffic signals or signal modifications (as warranted), a new bridge at Willow Creek M100-00-00 and all necessary appurtenances within the 100-foot right-of-way.

Expected Impact:
HDR Engineering, Inc. will provide the additional engineering services required for the project. Completion of the design and construction of...