Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: County Engineer
Secondary Department Head/Elected Official: Milton Rahman
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 230329
Vendor/Entity Legal Name (if applicable): Lee Construction & Maintenance dba LMC
MWBE Contracted Goal (if applicable): 30%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request that the County Judge execute an amendment to an agreement with Lee Construction & Maintenance dba LMC in the additional amount of $5,948,486 for job order contracting for small and large construction and/or construction related projects for Harris County for the period of June 4, 2025 - June 3, 2026, and for the County Clerk to execute any applicable bonds to be received (230329), MWBE Contracted Goal: 30%, MWBE Current Participation: 100%.
end
Background and Discussion:
Job Order Contract to be utilized as needed for Harris County for small/large construction related projects. Amendment will allow for additional funds to allow projects to continue through term.
Expected Impact:
N/A
Alternative Options:
Without master agreement, Harris County will be severely limited in the number of emergency projects that can be completed due to the lack of funding.
County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A
Additional notes ...
Click here for full text