Primary Department: Commissioner, Precinct 4
Primary Department Head/Elected Official: Lesley Briones, Commissioner
Managing Department: Commissioner, Precinct 4
Managing Department Head/Elected Official: Lesley Briones, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Commercial Paper
Investment Memo Type: Final Investment Memo
Project Name: Fiorenza Park East Upgrades
Project ID (if applicable): FIORENZA-EAST
Vendor Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Incremental Authorization Requested: $250,000.00
Total Estimated Project Cost: $250,000.00
Request Summary:
title
Request for approval of a Final Investment Memo for the Fiorenza Park East Upgrades project for an amount of $250,000.00, and request for approval of commercial paper funding in the amount of $250,000.00.
end
Project Description:
This project will be a safe play space designed as a community hub, bringing neighbors together and fostering community engagement in a space for children to meet, interact, and build friendships.
Building a playground with lighting significantly boosts community well-being by fostering physical activity, improving mental health, strengthening social bonds, enhancing safety (especially at night), and creating a vibrant hub for families and residents of all ages. It offers a free, inclusive space for children's development, and also creates a meeting spot for parents and caregivers, leading to greater neighborhood pride and engagement.
Anticipated Project Expenditures and Timeline:
Project Scope Breakdown
Estimated Cost
Estimated Completion
New playground equipment
$150,000.00
06/15/2026
Lighting
$50,000.00
06/15/2026
Installation
$50,000.00
06/15/...