Legislation Details

File #: 26-2549    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 4/6/2026 In control: Commissioners Court
On agenda: 4/16/2026 Final action: 4/16/2026
Title: Transmittal by the Office of the County Engineer of a correction to Job No. 25/0083-1 on a previously approved change in contract with Millis Equipment, LLC in connection with construction of Burnett Bayland Park - Design Phase - 2024, UPIN 24104MF3HC01, Precinct 4, to the corrected Job No. 25/0025-1.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): Job No. 25/0025, UPIN 24104MF3HC01
Vendor/Entity Legal Name (if applicable): Millis Equipment, LLC

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a correction to Job No. 25/0083-1 on a previously approved change in contract with Millis Equipment, LLC in connection with construction of Burnett Bayland Park - Design Phase - 2024, UPIN 24104MF3HC01, Precinct 4, to the corrected Job No. 25/0025-1.
end

Background and Discussion:
This transmittal is to correct a clerical error in the project number. The previously referenced Job No. 25/0083 listed on change in contract #1 is incorrect. The correct project number is Job No. 25/0025. No other changes are made to the scope, cost, or contract terms.

This correction will allow the bonding company to issue a rider to increase the bond.

Expected Impact:
Bond will not be allowed to be issued.

Alternative Options:
No alternative options.





County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: I: Increase access to safe, clean, and enjoyable green space.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): I1: Develop a countywide parks network and connectivity plan.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N3: Promote inc...