Legislation Details

File #: 26-2357    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 4/2/2026 In control: Commissioners Court
On agenda: 4/16/2026 Final action: 4/16/2026
Title: Request for approval of change in contract No. 1 with RES Environmental Operating Company LLC, for the floating islands at Reverend William and Audrey Lawson Stormwater Detention Basin, adding 22 calendar days (Clear Creek Watershed, Bond ID C-05, Project ID A500-08-00-W001, Job No. 25/0059, Precinct 1, MWBE Contracted Goal: 17.79%).
Attachments: 1. 041626 CIC RES ENVIRON A500-08-00-W001 PCT 1 backup.pdf
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): A500-08-00-W001
Vendor/Entity Legal Name (if applicable): RES Environmental Operating Company LLC

MWBE Contracted Goal (if applicable): 17.79%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of change in contract No. 1 with RES Environmental Operating Company LLC, for the floating islands at Reverend William and Audrey Lawson Stormwater Detention Basin, adding 22 calendar days (Clear Creek Watershed, Bond ID C-05, Project ID A500-08-00-W001, Job No. 25/0059, Precinct 1, MWBE Contracted Goal: 17.79%).
end

Background and Discussion:
This change in contract is needed to complete the construction contract for this project. Floating Islands at Rev
William and Audrey Lawson Stormwater Detention Basin include installation of two artificial floating island structures, and the construction of a canoe house, a monitoring station and a manhole for monitoring access to the existing outfall pipe. The purpose of this contract change is for the addition of 22 days to the contract due to manufacturing delays of the floating island units. The contract change includes a total of 22 days added to the contract.

Expected Impact:
This change will allow the contractor to construct the project so that Harris County can realize intended flood risk reduction benefits.

Alternative Options:
This is an active construction contract, so there are not many alternatives to approving a change order o...