Title: Request for approval of a change in contract with Precise Services, Inc., in connection with HCSFNC - TO6 - Connorvale Development, with an addition in the amount of $8,101.97, Job No. 24/0139-6, UPIN 21289MF1Z501, Precinct 2, MWBE Contracted Goal: 25.22%, MWBE Current Participation: 100%.
Attachments: 1. 26-2311-CIC-21289MF1Z501-Connovale-24-0139-6-Precise Svcs-P2-04162026
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0139, UPIN 21289MF1Z501
Vendor/Entity Legal Name (if applicable): Precise Services, Inc.

MWBE Contracted Goal (if applicable): 25.22%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services, Inc., in connection with HCSFNC - TO6 - Connorvale Development, with an addition in the amount of $8,101.97, Job No. 24/0139-6, UPIN 21289MF1Z501, Precinct 2, MWBE Contracted Goal: 25.22%, MWBE Current Participation: 100%.
end

Background and Discussion:
In response to the destruction wrought by Hurricane Harvey that underscored critical shortages in Harris County's inventory of affordable homes, Harris County's Single-Family New Construction Program (SFNCP) matches individuals and families with opportunities to purchase new affordable homes in growing developments throughout the county. Task Order 6: includes construction of roadways and sidewalks, Installation of sanitary sewer and storm systems, Pavement improvements, Construction of a lift station and detention ponds.
This change order is tied to PCO -13: The southeast curb ramp at Whistlestop and Aldus Grove failed TDLR inspection due to missing landings at the top of each ramp section. The original modified Type 3 curb ramp plan details were unclear regarding landings. To comply with ADA and TDLR standards, the existing ramp and sidewalk will be removed and replaced wi...

Click here for full text