Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0139, UPIN 21289MF1Z501
Vendor/Entity Legal Name (if applicable): Precise Services, Inc.
MWBE Contracted Goal (if applicable): 25.22%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services, Inc., in connection with HCSFNC - TO6 - Connorvale Development, with an addition in the amount of $8,101.97, Job No. 24/0139-6, UPIN 21289MF1Z501, Precinct 2, MWBE Contracted Goal: 25.22%, MWBE Current Participation: 100%.
end
Background and Discussion:
In response to the destruction wrought by Hurricane Harvey that underscored critical shortages in Harris County's inventory of affordable homes, Harris County's Single-Family New Construction Program (SFNCP) matches individuals and families with opportunities to purchase new affordable homes in growing developments throughout the county. Task Order 6: includes construction of roadways and sidewalks, Installation of sanitary sewer and storm systems, Pavement improvements, Construction of a lift station and detention ponds.
This change order is tied to PCO -13: The southeast curb ramp at Whistlestop and Aldus Grove failed TDLR inspection due to missing landings at the top of each ramp section. The original modified Type 3 curb ramp plan details were unclear regarding landings. To comply with ADA and TDLR standards, the existing ramp and sidewalk will be removed and replaced wi...