Primary Department: County Engineer
Primary Department Head/Elected Official:
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 240068 / UPIN 24103MF30K01
Vendor/Entity Legal Name (if applicable): McKenna Contracting, Inc
MWBE Contracted Goal (if applicable): 19.33%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with McKenna Contracting, Inc., in connection with Construction of Pickleball Courts at Russ Poppe Family Park, I.T. May Park, and Meyer Park, adding 93 calendar days, with a deduction in the amount of $17,131.25, Job No. 24/0068-1, UPIN 24103MF30K01, Precinct 3, MWBE Contracted Goal: 19.33%, MWBE Current Participation: 100%.
end
Background and Discussion:
Design and construction of (3) 64' x 100' x 5" thick Pickleball courts, 10' wide sidewalk that connects the adjacent parking lots to the courts as well as permitting a 25' x 25' concrete slab for a future shade canopy, 8' high perimeter chain-linked fence with (1) 4' wide and (1) 10' wide double gate.
This change in contract includes the following:
* Tree Removal (All Sizes) 4 EA ($2,100.00)
* Vehicular Gate (8FT Height) (10FT Wide Double Leaf) 1 EA ($2,258.00)
* Pedestrian Gate (8FT Height) 1 EA $1,575.00
* Concrete Pavement (Canopy) 69 SY ($7,607.25)
* Sodding for Erosion Control 1605 SY ($6,741.00)
The final adjustment (reconciliation of actual quanti...
Click here for full text