Legislation Details

File #: 26-2289    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 4/1/2026 In control: Commissioners Court
On agenda: 4/16/2026 Final action: 4/16/2026
Title: Request for approval to execute an agreement with WSB, LLC. in the amount of $64,244.00 for Professional Engineering services in connection with Asphalt Rehabilitation - Campbell Road - 2025, UPIN 25103MF3N001, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
Attachments: 1. Award-CPS-25103MF3N001-Asphalt Rehabilitation-Campbell Rd-2025-WBS-P3-4.9.26.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 25103MF3N001
Vendor/Entity Legal Name (if applicable): WSB LLC.

MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: 0% - Non-Divisible

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with WSB, LLC. in the amount of $64,244.00 for Professional Engineering services in connection with Asphalt Rehabilitation - Campbell Road - 2025, UPIN 25103MF3N001, Precinct 3, Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
end

Background and Discussion:

Precinct 3 is requesting the Office of the County Engineer to approve an agreement to provide construction phase services for Campbell Road mill and overlay with base repairs on the southern segment and complete reconstruction on the north segment.

Expected Impact:

The asphalt maintenance improvements will improve road quality and connectivity for the community in the specified area.

Alternative Options:

The alternative is not to complete the maintenance, and the road will continue to operate with the existing conditions.


County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county's transportation network in alignment with the County's Vision Zero plan.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Init...

Click here for full text