Legislation Details

File #: 26-2229    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/31/2026 In control: Commissioners Court
On agenda: 4/16/2026 Final action: 4/16/2026
Title: Request for approval of a change in contract with Forde Construction Co. in connection with final construction of Bridge Repair - Stuebner Airline Rd Bridge K100 - 2024, adding 1 calendar day, with an addition in the amount of $197,049.18, Job No. 24/0303-1, UPIN 24103MF3A801, Precinct 3, MWBE Contracted Goal: 30.62% MWBE Current Participation: 16.17%.
Attachments: 1. 26-2229-CIC-24103MF3A801-Stuebner Airline-24-0303-1-Final-Forde Constr-P3-04162026
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0303, UPIN 24103MF3A801
Vendor/Entity Legal Name (if applicable): Forde Construction Co.

MWBE Contracted Goal (if applicable): 30.62%
MWBE Current Participation (if applicable): 16.17%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Forde Construction Co. in connection with final construction of Bridge Repair - Stuebner Airline Rd Bridge K100 - 2024, adding 1 calendar day, with an addition in the amount of $197,049.18, Job No. 24/0303-1, UPIN 24103MF3A801, Precinct 3, MWBE Contracted Goal: 30.62% MWBE Current Participation: 16.17%.
end

Background and Discussion:
Bridge Repair - Stuebner Airline Rd Bridge K100 is located at Stuebner Airline Road, crossing over Cypress Creek. The Scope of Work for this project includes, but not limited to concrete spall repairs, bearing pads replacements, erosion control and slope regrading, Guardrail repairs, concrete channel lining, removal of structural - abutment backwall at the Stuebner Airline Rd bridge over HFCD Channel K100-00-00 (Cypress Creek) within Harris County, Precinct 3.

The Changes in contract include:
* An additional quantity of 1430 Cubic Yard of borrow material is needed for the existing line item #04 to complete the work proposed in the design plan with an additional cost of $168,740.00 and zero calendar days.
* An additional quantity of 225 Linear of metal beam guard fence is needed for the existing line item #011 ...

Click here for full text