Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0261, UPIN 24101MF3CT01
Vendor/Entity Legal Name (if applicable): Specialty Construction TX, LLC
MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: 0% - Minimal MWDBE Availability
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Specialty Construction TX, LLC, in connection with On-Call - Guardrail and Bridge Rail Repairs and Related Items at Various Locations, with no change in the contract amount, Job No. 24/0261-1, UPIN 24101MF3CT01, Precinct 1, Justification for 0% MWBE Participation Goal: 0% - Minimal MWBE Availability.
end
Background and Discussion:
Project includes the maintenance of guardrail and bridge rail repairs at various locations throughout Precinct 1. The change in contract is to include reconciliation of actual quantities used in construction with the estimated quantities included for bidding purposes. There will be zero days, and zero costs added to this contract. The Precinct has requested a new bid item to be added. The new bid item is only to establish the unit price and there is no change to the contract amount.
Change includes adding the following bid Item:
1- Item 54 - Galvanized Steel Traffic Railing ($417.00/LF) (PCO # 1)
All missing in the current bid.
Expected Impact:
Change allows Contractor to complete the outstanding work order within the Precinct 1 limits.
Alternative Options:
Maintain the original scope of the project.
County Stra...