Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: County Engineer
Secondary Department Head/Elected Official: Milton Rahman
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 250405
Vendor/Entity Legal Name (if applicable): SAS Concrete Construction, LLC
MWBE Contracted Goal (if applicable): 30.42%
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to SAS Concrete Construction, LLC in the amount of $3,505,610 for repair of various roads within Northshore area (2024) for the BetterStreets2Neighborhoods Community Program for Precinct 2, and for the County Clerk to execute any applicable bonds to be received (250405), MWBE Contracted Goal: 30.42%.
end
Background and Discussion:
This project is part of the Precinct 2 BetterStreets2Neighborhoods Community Program to enhance drivability and provide a safe driving environment in the Northshore Area. The project consists of replacing approximately 25,438 square yards of 8-inch concrete pavement, 15,025 square yards of 6-inch concrete curb in the Northshore Area, 4000 square yards of driveways and 300 square yards of concrete sidewalks.
Expected Impact:
This project seeks to enhance drivability in the city of Houston in the Northshore area by providing improvements to the roadway surface. The project also seeks to enhance walkability along Hollypark Drive by providing a sidewalk.
Alternative Options:
County Strategic Plan Goal: 1. Make Harris County safer and more just.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and...
Click here for full text