Legislation Details

File #: 26-2080    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/13/2026 In control: Commissioners Court
On agenda: 3/31/2026 Final action: 3/31/2026
Title: Request for approval of a change in contract with MC2 Civil LLC, in connection with final construction of E132-00-00 Mitigation Project, with a deduction in the amount of $209,206.01, Job No. 23/0429-3, UPIN 21090MF22E01, Precinct 3, MWBE Contracted Goal: 27%, MWBE Current Participation: 30.30%.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 23/0429, UPIN 21090MF22E01
Vendor/Entity Legal Name (if applicable): MC2 Civil LLC

MWBE Contracted Goal (if applicable): 27%
MWBE Current Participation (if applicable): 30.30%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with MC2 Civil LLC, in connection with final construction of E132-00-00 Mitigation Project, with a deduction in the amount of $209,206.01, Job No. 23/0429-3, UPIN 21090MF22E01, Precinct 3, MWBE Contracted Goal: 27%, MWBE Current Participation: 30.30%.
end

Background and Discussion:
The E132-00-00 Mitigation project is located in Northwest Harris County in Precinct 3. More specifically, it lies to the Southwest intersection of N Eldridge Parkway and Cypress North Houston Road. E132-00-00 is a HCFCD drainage channel, a tributary of White Oak Bayou (E100-00-00) and serves as one of the outfall systems for the subdivisions of Bernadine Estates, Barwood, Tower Oaks and Tower Oaks Meadows. The scope of work for this
project consists of channel improvements to accommodate increased conveyance due to the subdivision's drainage Improvement projects.

The change in contract includes the following:

The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.

? The increase of quantities on overrun line-item numbers 22, 23, 32, 36, 41, 44, 45, 56, 57, 58, 64 and 65 for an addition in the amount...

Click here for full text