Legislation Details

File #: 26-1901    Version: 1 Name:
Type: Contract - Award Status: Passed
File created: 3/9/2026 In control: Commissioners Court
On agenda: 3/19/2026 Final action: 3/19/2026
Title: Request for approval of an award on the basis of low bid to MetroCity, LLC in the amount of $1,162,059 for reconstruction and widening of Peek Road from 1600' North of the Grand Parkway to 580' South of Clay Road (2021) for Precinct 4, and for the County Clerk to execute any applicable bonds to be received (250362), MWBE Contracted Goal: 32.03%.
Attachments: 1. 26-1901 Award Job No. 250362 MetroCity, LLC.pdf
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): 250362
Vendor/Entity Legal Name (if applicable): MetroCity, LLC

MWBE Contracted Goal (if applicable): 32.03%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of low bid to MetroCity, LLC in the amount of $1,162,059 for reconstruction and widening of Peek Road from 1600' North of the Grand Parkway to 580' South of Clay Road (2021) for Precinct 4, and for the County Clerk to execute any applicable bonds to be received (250362), MWBE Contracted Goal: 32.03%.
end

Background and Discussion:
The scope of this project consists of the widening of Peek Road from 1600' North of the Grand Parkway to 580' South of Clay Road to convert the existing two-lane roadway to a four-lane boulevard roadway section. The expansion includes installing additional curb inlets in the southbound lanes to improve drainage, designed to meet Atlas 14 100-year storm event criteria.

Expected Impact:
Awarding the contract will allow the recommended bidder to proceed with construction. The project will complete the boulevard segment of Peek Road, improve traffic flow, and provide positive drainage through the installation of additional inlets.

Alternative Options:
The alternative is not to award the contract. If no action is taken, road widening and associated improvements will not be constructed.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably...

Click here for full text