Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Secondary Department: Commissioner, Precinct 2
Secondary Department Head/Elected Official: Adrian Garcia, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 24102MF3K301
Vendor/Entity Legal Name (if applicable): Cobb, Fendley & Associates, Inc.
MWBE Contracted Goal (if applicable): 9.90%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Cobb, Fendley & Associates, Inc., in the amount of $461,032.75 for professional engineering services in connection with Corridor Study - Reimagine Clinton Drive Galena Manor to Crown Street, UPIN 24102MF3K301, Precinct 2, MWBE Contracted Goal: 9.90%.
end
Background and Discussion:
Clinton Drive from Galena Manor to Crown Street located in Precinct 2 is part of the High Injury Network identified in Harris County's Vision Zero Action Plan. The corridor is being examined for potential improvements focusing on safety and mobility. The study will include stakeholder and public engagement to seek input on infrastructure issues and potential improvements to the corridor. This project will provide professional engineering services for approximately 9,000 LF (1.70 mi) of Clinton Drive from 320' west of Galena Manor to Crown Street. As per the request and funding from Precinct 2, the Office of the County Engineer will be conducting the study with requested consultant assistance from Cobb, Fendley & Associates, Inc.
Expected Impact:
This study will establish existing conditions baseline for the community, including those wh...