Legislation Details

File #: 26-1732    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 3/5/2026 In control: Commissioners Court
On agenda: 3/19/2026 Final action: 3/19/2026
Title: Transmittal by the Office of the County Engineer of a substantial completion certificate with Econ Development, Inc., in connection with Parkway Forest Subdivision Drainage Improvements - 2018 (P122-00-00 Basin), Job No. 24/0372, UPIN 19101MF14P02, Precinct 1, MWBE Contracted Goal: 16%, MWBE Current Participation: 36.59%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): Job No. 24/0372, UPIN 19101MF14P02
Vendor/Entity Legal Name (if applicable): Econ Development, Inc.

MWBE Contracted Goal (if applicable): 16%
MWBE Current Participation (if applicable): 36.59%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Transmittal by the Office of the County Engineer of a substantial completion certificate with Econ Development, Inc., in connection with Parkway Forest Subdivision Drainage Improvements - 2018 (P122-00-00 Basin), Job No. 24/0372, UPIN 19101MF14P02, Precinct 1, MWBE Contracted Goal: 16%, MWBE Current Participation: 36.59%.
end

Background and Discussion:
The Substantial Completion Certificate provides documentation that a capital improvement project meets the qualifications of Substantial Completion in accordance with the Contract Documents as determined by the County Engineer. Substantial Completion establishes the date on which a capital improvement enters service as a Harris County asset. The establishment and reporting of this date are important for all governmental entities as outlined in the GASB Statement #34, Capital Assets & Depreciation Guidance, August 31, 2001. These certificates provide a method by which Harris County may document and record this date.


Expected Impact:
N/A

Alternative Options:
N/A

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: H: Improve the conditi...

Click here for full text