Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey
Regular or Supplemental RCA: Regular RCA
Type of Request: Utility Agreement
Project ID (if applicable): 19103MF14801
Vendor/Entity Legal Name (if applicable): CenterPoint Energy Houston Electric, LLC
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute a Service Outlet Location Statement for the removal of the existing overhead facilities with CenterPoint Energy Houston Electric, LLC within the Tower Oaks Plaza Subdivision, at no cost to Harris County, that are currently in conflict with Harris County Flood Control's access requirements, UPIN 19103MF14801, Precinct 3.
end
Background and Discussion:
The Tower Oaks Plaza Subdivision Drainage Improvement Project is designed to enhance stormwater management within the subdivision. The project aims to reduce flood risk and increase community resiliency by mitigating potential structural flood damage to homes in the Tower Oaks Plaza community. Specifically, the project will provide drainage improvements designed to achieve a 50-year level of service, helping to protect properties and infrastructure from significant flooding events.
Expected Impact:
Approval of the Service Outlet Location (SOL) statement will allow CenterPoint Energy Houston Electric to remove the overhead facilities, located at or near 13410 Forest Cove Dr, Cypress, TX 77429. Removal of the overhead facilities is essential to prevent obstruction of access required by Harris County...
Click here for full text