Legislation Details

File #: 26-1714    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 3/5/2026 In control: Commissioners Court
On agenda: 3/19/2026 Final action: 3/19/2026
Title: Request for approval of a change in contract with Environmental Allies, Inc., in connection with Humble Road Place and Parkland Estates Subdivisions Drainage Improvements - 2018, with an addition in the amount of $186,850.00, Job No. 25/0113-1, HC Road Fund, UPIN 21090MF22H01, Precincts 1 and 2, MWBE Contracted Goal: 24.53%, MWBE Current Participation: 21.54%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 25/0113, UPIN 21090MF22H01
Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.

MWBE Contracted Goal (if applicable): 24.53%
MWBE Current Participation (if applicable): 21.54%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies, Inc., in connection with Humble Road Place and Parkland Estates Subdivisions Drainage Improvements - 2018, with an addition in the amount of $186,850.00, Job No. 25/0113-1, HC Road Fund, UPIN 21090MF22H01, Precincts 1 and 2, MWBE Contracted Goal: 24.53%, MWBE Current Participation: 21.54%.
end

Background and Discussion:
The project involves installing storm sewers beneath the existing ditches throughout the Humble Road Place and Parkland Estates subdivisions and constructing a detention basin to offset the increased flows resulting from the improvements.

The change in contract includes the following:

The line items are adjusted to reconcile overrun and underrun quantities on the project for completion of the proposed scope of work.

* The increase in quantities on overrun line-item numbers 52, 54, and 86 for an addition in the amount of $186,850.00.00.

The above additions result in a net change in the amount of $186,850.00 and 0 calendar days.

Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in ...

Click here for full text