Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0359, UPIN 19101MF16R01
Vendor/Entity Legal Name (if applicable): Environmental Allies Inc.
MWBE Contracted Goal (if applicable): 29.74%
MWBE Current Participation (if applicable): 38.00%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Environmental Allies Inc, in connection with North Forest Subdivision Drainage Improvements 2018, with an addition in the amount of $93,677.00, Job No. 24/0359-1, Grant Fund, UPIN 19101MF16R01, Precinct 1, MWBE Contracted Goal: 29.74%, MWBE Current Participation: 38.00%.
end
Background and Discussion:
The project includes an underground storm sewer system and a wet bottom detention basin. Project also include full-width roadway pavement reconstruction, sidewalk reconstruction and widening, and joint and crack cleaning and sealing throughout the North Forest Subdivision.
The change in contract includes the following:
The line items are adjusted to reconcile overrun quantities on the project for completion of the proposed scope of work.
* The increase in quantities on overrun line-item numbers 25, 26, 32, and 43 for an addition in the amount of $93,677.00.
The above additions result in the amount of $93,677.00 and 0 calendar days.
Expected Impact:
This project seeks to reduce flooding and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the North Forest Subdivision.
Alter...