Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0408, UPIN 19102MF15W01
Vendor/Entity Legal Name (if applicable): Precise Services Inc.
MWBE Contracted Goal (if applicable): 22.81%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Precise Services Inc., in connection with Cedar Bayou Park East and West Subdivision Drainage Improvements - 2018, adding 19 calendar days, with an addition in the amount of $441,341.63, Job No. 24/0408-1, Bond Fund, UPIN 19102MF15W01, Precinct 2, MWBE Contracted Goal: 22.81%, MWBE Current Participation: 100%.
end
Background and Discussion:
This project entails the construction of storm sewer drainage to convey drainage in the Cedar Bayou Park East
and West Subdivision from Sjolander Road to Bayou Boulevard.
The change in contract includes the following:
Added new line items to the bid items of the project for completion of the proposed scope of work.
? Added new line item 125 for flowable fill for culverts - (RFI-53/PCO-14) for an addition in the amount of $81,900.00 and 10 days.
? Added new line item 126 for temporary driveway access - (RFI-64/PCO-15) for an addition in the amount of $199,947.85 and 0 days.
? Added new line item 127 for construction entrance/exit - (RFI-71/PCO-16) for an addition in the amount of $5,600.00 and 0 days.
? Added new line item 128 for waterline relocation at Sjolander and Archer Rd - (RFI-72/PCO-17) for an a...
Click here for full text