Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Secondary Department: Choose an item.
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): UPIN 19103MF12K01
Vendor/Entity Legal Name (if applicable): Amani Engineering Inc.
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of a study report prepared by Amani Engineering Inc., for Tower Oaks Meadows Subdivision Drainage Improvements - 2018, UPIN 19103MF12K01, Precinct 3.
end
Background and Discussion:
The project area is located in the Northwest area bounded by Barwood Subdivision on the North, N Eldridge Pkwy on the East, Fallbrook Dr on the South, and Marrs Dr on the West. The subdivision is specifically bounded on the West by HCFCD Unit E133-00-00, on the East by HCFCD Unit E132-00-00. The Tower Oaks Meadows Subdivision primarily served by roadside ditch drainage systems that are directed East to N Eldridge Pkwy, West to HCFCD Unit E133-00-00 and North to an existing storm sewer within a back lot easement on the common line between Tower Oaks Meadows and Barwood Subdivision. The scope of work for this project consists of storm sewer improvements by regrading ditches and providing additional capacity underneath ditches to accommodate for increased conveyance, and full roadway reconstruction in the subdivision.
Expected Impact:
This project seeks to reduce flood risk and strengthen resiliency in Harris County by assisting in the alleviation of structural flood damage to homes in the community. Thi...
Click here for full text