Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: County Engineer
Secondary Department Head/Elected Official: Milton Rahman
Regular or Supplemental RCA: Supplemental RCA
Type of Request: Contract - Award
Project ID (if applicable): 250304
Vendor/Entity Legal Name (if applicable): E Contractors USA LLC
MWBE Contracted Goal (if applicable): 12.10%
MWBE Current Participation (if applicable): n/a
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request by the Office of the Purchasing Agent for approval of an award on the basis of lowest priced proposal meeting requirements with E Contractors USA LLC in the amount of $2,438,571 for construction of Fire Marshal training facility for the Office of the County Engineer and for the County Clerk to execute any applicable bonds to be received (250304), MWBE Contracted Goal: 12.10%.
...end
Background and Discussion:
A training facility will be constructed at the Fire Marshal's Office located at 2318 Atascocita Rd, Humble TX. This training classroom will be used for in-person and hybrid training for public safety and industrial partners. The training facility will be 5,750 square feet, with two restrooms, a kitchen, four offices, and support space. The training classroom will have full audio-visual capabilities for quality education delivery both in person, virtually, or in combination.
Expected Impact:
The construction of the Fire Marshal Training Facility will be able to provide more fire and life safety training for law enforcement, fire, EMS, educational entities, and industrial partners.
Alternative Options:
The alternative is to continue with the current training facility; however, the current facility cannot accommodate all requests for fi...