Title: Request for approval of an amendment to an agreement with HR Green, Inc. in the amount of $51,000.00 for Professional Engineering Services in connection with Hufsmith-Kohrville Rd 3, UPIN 15104M23NP03, Precinct 3 (previously Precinct 4), Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
Sponsors: Mony Hossain
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, P.E., Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 15104M23NP03
Vendor/Entity Legal Name (if applicable): HR Green, Inc.

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with HR Green, Inc. in the amount of $51,000.00 for Professional Engineering Services in connection with Hufsmith-Kohrville Rd 3, UPIN 15104M23NP03, Precinct 3 (previously Precinct 4), Justification for 0% MWBE Participation Goal: N/A - project was awarded prior to launch of County's M/WBE Program.
end

Background and Discussion:

The County executed an agreement for Professional Engineering Services with HR Green, Inc. on March 10, 2015, and now seeks to amend the agreement for ninth time. This amendment will facilitate the re-design of the underground storm sewer system to account for the flow being received from the Hufsmith-Kohrville Road Segment 4.

Expected Impact:

This action will allow the firm to incorporate the necessary design changes to size the storm sewer according to the flow received from the north segment.

Alternative Options:
The alternative is to not revise the plans, and the plans will not be compatible with the needs of the adjacent project segment.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure....