Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): UPIN 25101MF3N301
Vendor/Entity Legal Name (if applicable): Infrastructure Engineering, Inc.
MWBE Contracted Goal (if applicable): 19.6%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with Infrastructure Engineering, Inc. in the amount of $244,032.00 for Professional Engineering Services in connection with Hafer Road improvements from FM 1960 to Skywood Drive, UPIN 25101MF3N301, Precinct 1, MWBE Contracted Goal: 19.6%.
end
Background and Discussion:
Hafer Road is a local collect roadway. The project is to convert 1 mile 2-lane asphalt roadway with ditches to a 2-lane concrete roadway with storm sewer and sidewalk/share-use-path from FM 1960 to Skywood Lane. The amendment is to perform the community engagement, roundabout design at Butterfield Road intersection, additional sidewalk and other traffic calming options.
Expected Impact:
The proposed improvements will provide safe conditions for vehicles and pedestrians traffic based on the community input.
Alternative Options:
No alternative options. Project would lack public input information.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county's transportation networ...
Click here for full text