File #: 26-1227    Version: 1 Name:
Type: Interlocal Agreement Status: Passed
File created: 2/11/2026 In control: Commissioners Court
On agenda: 2/26/2026 Final action: 2/26/2026
Title: Request for approval to execute an interlocal agreement with Clear Creek Independent School District for swale revisions to improve drainage and reduce parking lot flooding adjacent to FM 528, UPIN 26102MF3Y901, Precinct 2, Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement.
Sponsors: Mony Hossain
Attachments: 1. 26-1227-Partnership-26102MF3Y90-Brookside Drain Rep.-CCISD-P2-2.26.26 RCA.pdf
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 2
Secondary Department Head/Elected Official: Adrian Garcia, Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Interlocal Agreement

Project ID (if applicable): UPIN 26102MF3Y901
Vendor/Entity Legal Name (if applicable): Clear Creek Independent School District

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with Clear Creek Independent School District for swale revisions to improve drainage and reduce parking lot flooding adjacent to FM 528, UPIN 26102MF3Y901, Precinct 2, Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement.
end

Background and Discussion:
Brookside Intermediate, constructed in 1995, was the campus most significantly affected by Hurricane Harvey in 2017. Continued development in the surrounding area has contributed to ongoing issues with residual ponding, which has impacted parking areas and posed a risk of water intrusion into the building. Revising the swales will establish positive drainage flow to the designated underground storm sewer system, reducing the potential for surface flooding.

Expected Impact:
This project will provide better drainage flow, reduce ponding, and prevent building water intrusion.

Alternative Options:
If no action is taken, there may be a negative flooding impact for surrounding communities.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastr...