File #: 26-0960    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/29/2026 In control: Commissioners Court
On agenda: 2/12/2026 Final action: 2/12/2026
Title: Request for approval to extend a contract and correct the vendor name from Two Sons Environmental Services (as approved) to PUR-MC, INC. dba Two Sons Environmental Services (corrected) for new construction and maintenance of on-site sewage facilities at various locations and related items for the period of April 1, 2026 - July 1, 2026, with no increase in pricing (210021), Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
Attachments: 1. 26-0960 Extension and Corrected Vendor Name Job No. 210021 - PUR-MC, INC. dba Two Sons Environmental Services
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: County Engineer
Secondary Department Head/Elected Official: Milton Rahman

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): 210021
Vendor/Entity Legal Name (if applicable): Two Sons Environmental Services (as approved); PUR-MC, INC. dba Two Sons Environmental Services (corrected)

MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: 0% - Non-Divisible

Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.

Request Summary (Agenda Caption):
title
Request for approval to extend a contract and correct the vendor name from Two Sons Environmental Services (as approved) to PUR-MC, INC. dba Two Sons Environmental Services (corrected) for new construction and maintenance of on-site sewage facilities at various locations and related items for the period of April 1, 2026 - July 1, 2026, with no increase in pricing (210021), Justification for 0% MWBE Participation Goal: 0% - Non-Divisible.
end

Background and Discussion:
A countywide term contract was created to provide the Office of the County Engineer and the Precincts
with services to include new construction of On-Site Sewage Facilities and monthly maintenance and
operation of existing On-Site Sewage Facilities at various locations within Harris County. Request for approval to extend a contract and to correct the vendor name from Two Sons Environmental Services (as approved) to PUR-MC, INC. dba Two Sons Environmental Services (corrected) for New Construction and Maintenance of On-Site Sewage Facilities at Various Locations and Related Items for the Office of the County Engineer. This project is bonded on a per project basis.

Expected Impact:
The Office of the County Engineer and each Pre...