Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer
Secondary Department: Commissioner, Precinct 4
Secondary Department Head/Elected Official: Lesley Briones, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): UPIN 25104MF3UU01
Vendor/Entity Legal Name (if applicable): AIG Technical Services, LLC.
MWBE Contracted Goal (if applicable): 19.82%
MWBE Current Participation (if applicable): 0%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with AIG Technical Services, LLC, in the amount of $1,411,367.00 for Professional Architecture and Engineering Services in connection with Hike and Bike Trail - Mason Creek Trail Extension - 2024, UPIN 25104MF3UU01, Precinct 4, MWBE Contracted Goal: 19.82%.
end
Background and Discussion:
The project is located on the west side of Harris County (PCT 4), near the intersection of Grand Parkway 99 and Franz Road. Project scope includes design and construction of shared use hike and bike primary and secondary trails consisting of asphalt, concrete paths, local street crossings, bridge crossings, curb ramps and high visibility cross walks with regulatory signage.
Expected Impact:
The proposed hike and bike trail extension will improve specified public pedestrian paths and facilitate safer public mobility.
Alternative Options:
The County could elect to fund the requested task or choose to reject it. However, if not approved, the project may not be constructed. As a result, the community may not have improved pedestrian paths to facilitate safer public mobility.
County Strategic Plan Goal: 2. Connect our community...