Title: Request for approval of an amendment to an agreement with Civitas Engineering Group, Inc. in the amount of $41,400.00 for Professional Services in connection with Cypress Station Area Phase 2 project, UPIN 24101MF3E401, Precinct 1, MWBE Contracted Goal: 19.6%.
Attachments: 1. 26-0933-CIC-UPIN 24101MF3E401-PSA-Sidewalk Cypress Sta Ph 2-Civitas Engineering-P1-01-08-2026
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): UPIN 24101MF3E401
Vendor/Entity Legal Name (if applicable): Civitas Engineering Group Inc

MWBE Contracted Goal (if applicable): 19.6%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with Civitas Engineering Group, Inc. in the amount of $41,400.00 for Professional Services in connection with Cypress Station Area Phase 2 project, UPIN 24101MF3E401, Precinct 1, MWBE Contracted Goal: 19.6%.
end

Background and Discussion:
The amendment is to perform the topo and existing right of way survey for three additional streets to properly design the sidewalk.

Expected Impact:
Provide enhanced mobility for pedestrians within Cypress Station Area.

Alternative Options:
No Alternative options. Project will be lack of basic design information.

County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: F: Ensure safety and security for all using the county's transportation network in alignment with the County's Vision Zero plan.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): G1: Expand pedestrian and cyclist infrastructure on County-managed roads,
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative...