Legislation Details

File #: 26-0929    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/29/2026 In control: Commissioners Court
On agenda: 2/12/2026 Final action: 2/12/2026
Title: Request for approval of a change in contract with Environmental Allies, Inc., in connection with the construction of Lockwood Overpass Parking Lot & Improvements, adding 10 calendar days, with no change in the amount, Job No. 24/0407-2, UPIN 21102MF1SM01, Precinct 2, MWBE Contracted Goal: 25.21%, MWBE Current Participation: 10.80%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0407, UPIN 21102MF1SM01
Vendor/Entity Legal Name (if applicable): Environmental Allies, Inc.

MWBE Contracted Goal (if applicable): 25.21%
MWBE Current Participation (if applicable): 10.80%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
...title
Request for approval of a change in contract with Environmental Allies, Inc., in connection with the construction of Lockwood Overpass Parking Lot & Improvements, adding 10 calendar days, with no change in the amount, Job No. 24/0407-2, UPIN 21102MF1SM01, Precinct 2, MWBE Contracted Goal: 25.21%, MWBE Current Participation: 10.80%.
...end

Background and Discussion:
The project involves constructing new roadways-Marron Park Way and Maplewood Trailhead Lane-and new parking areas beneath the Lockwood Overpass, along with a traffic signal at the intersection of Marron Park Way and Lockwood Drive. It also includes the construction of a retaining wall, stormwater drainage system, and extensions of water and sanitary lines connecting to existing utilities along Lockwood Drive. Additional improvements consist of sidewalks, trails, and the installation of decorative streetlight, pedestrian pathway, and parking lot lighting. This change in contract includes:

PCO#4 - The quantity of stamped concrete has increased substantially due to a miscalculation during the PS&E phase, where the initial assumed quantity was 6 SF, while the actual quantity scaled from the plans is approximately 975 SF. Althou...