Legislation Details

File #: 26-0867    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/27/2026 In control: Commissioners Court
On agenda: 2/12/2026 Final action: 2/12/2026
Title: Request for approval of a change in contract with DCE Construction, Inc., in connection with final construction of Maintenance - BS2N Beamer Road - 2024, adding 15 calendar days, with an addition in the amount of $100,345.86, Job No. 25/0049-1, UPIN 24102MF3B301, Precinct 2, MWBE Contracted Goal: 18.75%, MWBE Current Participation: 18.85%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 25/0049, UPIN 24102MF3B301
Vendor/Entity Legal Name (if applicable): DCE Construction, Inc.

MWBE Contracted Goal (if applicable): 18.75%
MWBE Current Participation (if applicable): 18.85%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
...title
Request for approval of a change in contract with DCE Construction, Inc., in connection with final construction of Maintenance - BS2N Beamer Road - 2024, adding 15 calendar days, with an addition in the amount of $100,345.86, Job No. 25/0049-1, UPIN 24102MF3B301, Precinct 2, MWBE Contracted Goal: 18.75%, MWBE Current Participation: 18.85%.
...end

Background and Discussion:
The project includes the rehabilitation of approximately 1.7 miles of concrete pavement along Beamer Road in Harris County Precinct 2 to improve roadway conditions and safety. Work consists of full-depth concrete pavement repairs, crack sealing, replacement of traffic signal detection loops, stormwater inlet repairs, pavement striping, traffic control, and final site restoration in accordance with the approved plans and engineering standards.

PCO#1 - The original plan calls for the removal and replacement of the concrete panel from Sagerock Drive to Scarsdale Boulevard. However, during a field review, it was determined that the existing guardrail must be temporarily removed and stored to allow the contractor to complete the concrete paving work. This scope revision is necessary because the guardrail obstructs access to...