Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0161, UPIN 22103MF2E801
Vendor/Entity Legal Name (if applicable): Queen Constructors, LLC
MWBE Contracted Goal (if applicable): 29.72%
MWBE Current Participation (if applicable): 54.39%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Queen Constructors, LLC., in connection with final construction of Harris County Precinct Three for LMI Sidewalks and Trail Project (Phase 2), adding 48 calendar days, with an addition in the amount of $17,997.82, Job No. 24/0161-1, UPIN 22103MF2E801, Precinct 3, MWBE Contracted Goal: 29.72%, MWBE Current Participation: 54.39%.
end
Background and Discussion:
This project involves the construction of 5-ft wide sidewalks along Huffmeister, between Fleur De Lis and Cypress North Houston, Harris County within Precinct 3. This project is federally funded by the U.S. Housing and Urban Development Department (HUD) through the Harris County Community Services Department (HCCSD).
This final change order is for an addition of the final adjustment in the amount of $17,997.82 and includes quantity adjustments of existing items for final values.
Final Adjustment is the reconciliation of actual quantities used in construction against the bid quantities.
The final change in contract includes the following:
PCO-3, Proposed Swale/Drainage System = $7,950.00
PCO-4, AT&T Utility Conflict Delay = $0.00, Time: 48 Days
PCO-5, Final Adjustment = $10,047.8...