Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): UPIN - 20104MF1C801
Vendor/Entity Legal Name (if applicable): Vogler & Spencer Engineering, Inc.
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable):
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a study report prepared by Vogler & Spencer Engineering, Inc. in connection with Cutten Rd - from south of Bavaria Dr to Cossey Rd - 2019, UPIN 20104MF1C801, Precinct 3.
end
Background and Discussion:
The Cutten Rd project general scope is design and construction of a standard four (4) lane concrete boulevard extension of Cutten Rd from 270-ft north of Magnolia Dr. to Cossey Rd. in 100-ft right of way with 32-ft raised medians and underground storm sewer. The project includes a new bridge and upgrade to an existing culvert bridge. We are coordinating with the local municipal utility district for the drainage component.
Expected Impact:
The road expansion project will improve the road quality for the community in the specified area.
Alternative Options:
Without this project, the road cannot be improvement properly. The goal is to provide better mobility and/or eliminate hazards from the roadway as requested by the Precinct.
County Strategic Plan Goal: 1. Make Harris County safer and more just.
County Strategic Plan Objective: G: Expand and optimize multimodal transportation options.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Eco...