Legislation Details

File #: 26-0568    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 1/13/2026 In control: Commissioners Court
On agenda: 1/29/2026 Final action: 1/29/2026
Title: Request for approval of a change in contract with McCory Engineering, in connection with the construction of Trail - Pinckney Trail - (TIRZ 21) 2021, adding 120 calendar days, with an addition in the amount of $20,000.00, Job No. 24/0215-3, UPIN 22102MF2D501, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 100%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0215, UPIN 22102MF2D501
Vendor/Entity Legal Name (if applicable): McCory Engineering

MWBE Contracted Goal (if applicable): 25%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with McCory Engineering, in connection with the construction of Trail - Pinckney Trail - (TIRZ 21) 2021, adding 120 calendar days, with an addition in the amount of $20,000.00, Job No. 24/0215-3, UPIN 22102MF2D501, Precinct 2, MWBE Contracted Goal: 25%, MWBE Current Participation: 100%.
end

Background and Discussion:
The project consists of constructing approximately 750 feet a 10-ft-wide hike and bike trail from the White Oak Bayou Greenway Trail to the intersection of Fletcher Street and Pinckney Street. The project will also include a proposed 200-ft long retaining wall with a concrete swale, approximately 900 LF of varying size storm sewer along with inlets and manholes, a headwall, grass-lined swales, bollards, permanent street and trail signs, handrails, waterline and sanitary line adjustments, benches, trash receptacles, and pavement markings accompanying the trail.

The Changes in contract include:
* An additional 5 months of stormwater pollution prevention (SWPPP) is needed for the existing line item #062 to properly manage stormwater runoff from the construction site and to account for unpaid SWPPP services for July through December. This cha...

Click here for full text