Legislation Details

File #: 26-0563    Version: 1 Name:
Type: Transmittal Status: Accepted
File created: 1/13/2026 In control: Commissioners Court
On agenda: 1/29/2026 Final action: 1/29/2026
Title: Transmittal by the Flood Control District of a preliminary engineering report by Consor Engineers, Inc., dated September 1, 2025, and titled Preliminary Engineering Report - Q100-00-00-P003 from IH-10 to SH-146, Bond Map ID F-46, Channel Conveyance Improvements (Cedar Bayou Watershed, Precinct 2).
Primary Department: Flood Control District
Primary Department Head/Elected Official: Tina Petersen, Ph.D., P.E., Executive Director

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Transmittal

Project ID (if applicable): Q100-00-00-P003
Vendor/Entity Legal Name (if applicable): N/A

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Transmittal by the Flood Control District of a preliminary engineering report by Consor Engineers, Inc., dated September 1, 2025, and titled Preliminary Engineering Report - Q100-00-00-P003 from IH-10 to SH-146, Bond Map ID F-46, Channel Conveyance Improvements (Cedar Bayou Watershed, Precinct 2).
end

Background and Discussion:
This purpose of this court action is to transmit a preliminary engineering report by Consor Engineers, dated September 1, 2025, and titled Preliminary Engineering Report - Q100-00-00-P003 from IH-10 to SH-146, Bond Map ID F-46, Channel Conveyance Improvements located in the Cedar Bayou watershed.

Expected Impact:
The acceptance of this PER will allow the Flood Control District to close out the PER stage of the project.

Alternative Options:
The alternative should this PER not be approved is that the Flood Control District will not be able to close out the project.

County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: H: Improve the condition and resilience of County transportation, flood control, and other infrastructure.
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
...

Click here for full text