Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP
Managing Department: County Engineer
Managing Department Head/Elected Official: Milton Rahman, PhD, P.E, PMP, CFM, ENV-SP
Regular or Supplemental RCA: Regular RCA
Type of Request: Investment Memo
Investment Memo Type: Change Investment Memo
Project Name: Downtown Complex Tunnel System Repair and Mitigation
Project ID (if applicable): MF0X2
Vendor Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Achievement (if applicable): N/A
Justification for 0% MWDBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Incremental Authorization Requested: $1,500,000
Total Estimated Project Cost: $5,467,400
Request Summary:
title
Request for approval of a Change Investment Memo for the Downtown Complex Tunnel System Repair and Mitigation projects, for an incremental amount of $1,500,000.00 for a total of $5,467,400 and a request for approval of commercial paper funding in the amount of $1,500,000.00 for a total allocation of $5,470,000.
end
Project Description:
The purpose is to upgrade the Caroline Street Tunnel (FEMA to reimburse the funds). FEMA covers two projects in their scope:
1. Construction of the Downtown Tunnel Flood Mitigation Lift Station (currently under construction)
2. Construction of the Restoration of the Caroline Street Tunnel
This request is for the construction of the restoration of the Caroline Street Tunnel, which involves demolition and refurbishment of damaged floor, walls, and ceiling surfaces and finishes, as well as electrical light fixtures. These refurbishments will include mitigation upgrades, such as resilient wall panels and polished concrete flooring surfaces, to minimize damage during future floodin...
Click here for full text