Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD
Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 250308
Vendor/Entity Legal Name (if applicable): C.A. Walker, Inc. dba C.A. Walker Construction
MWBE Contracted Goal (if applicable): 23.73%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable):
Justification for 0% Grant Indirect Costs Rate (if applicable): Choose an item.
Request Summary (Agenda Caption):
title
Request for approval of an award on the basis of only proposal meeting requirements to C.A. Walker, Inc. dba C.A. Walker Construction in the amount of $2,800,000 for various improvements to the John and Hazel Biggers Campus for Precinct 1, and for the County Clerk to execute any applicable bonds to be received (250308), MWBE Contracted Goal: 23.73%.
end
Background and Discussion:
Precinct 1 intends to complete a surface parking lot north of the Precinct 1 complex. The project is to convert existing railway and adjacent ROW for the construction of a parking lot located at 2787 El Camino St, Houston, TX 77054
Expected Impact:
Approval of this request will enable the construction of a new parking lot, increasing on-site parking capacity by 148 spaces, thereby improving operational functionality, circulation, and accessibility at the Precinct 1 facility. The additional parking will support current and future staffing levels, fleet needs, and daily operations, reduce congestion and improve overall site efficiency.
Alternative Options:
None identified that adequately meet operational and site requirements.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintain...
Click here for full text