Legislation Details

File #: 26-0345    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/29/2025 In control: Commissioners Court
On agenda: 1/8/2026 Final action: 1/8/2026
Title: Request for approval of additional funds to The Brandt Companies, LLC in the amount of $270,480 for additional work for each location due to unforeseen field conditions at each park for emergency generator installation at various locations for Precinct 3, in connection with a Choice Partners, a division of Harris County Department of Education Cooperative award approved by Commissioners Court on June 26, 2025, Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement.
Attachments: 1. 26-0345 (REVISED) Choice Partners Additional Funds Contract 00002331 - The Brandt Companies, LLC
Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom Ramsey

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): N/A
Vendor/Entity Legal Name (if applicable): The Brandt Companies, LLC

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of additional funds to The Brandt Companies, LLC in the amount of $270,480 for additional work for each location due to unforeseen field conditions at each park for emergency generator installation at various locations for Precinct 3, in connection with a Choice Partners, a division of Harris County Department of Education Cooperative award approved by Commissioners Court on June 26, 2025, Justification for 0% MWBE Participation Goal: Exempt - Interlocal/Cooperative Agreement.
end

Background and Discussion:
This project's intent is to install full facility backup generators for 9 critical facilities/community centers in Precinct 3. These facilities will serve as emergency shelters and cooling & warming centers for constituents after natural disasters. The project involves design, procurement, constructing, and installing equipment, and fencing to protect generators

Expected Impact:
Project will make critical facilities more responsive to natural disasters by providing back-up power in the event of electricity loss.

Alternative Options:
N/A

County Strategic Plan Goal: 5. Minimize the impact of climate change and disasters.
County Strategic Plan Objective: R: Enhance disaster preparedness, response, recovery, ...

Click here for full text