Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, Commissioner
Regular or Supplemental RCA: Regular RCA
Type of Request: Interlocal Agreement
Project ID (if applicable): 26103MF3ZX01
Vendor/Entity Legal Name (if applicable): Harris County Municipal Utility District 132
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an interlocal agreement with Harris County Municipal Utility District No. 132 for the Golf Villas Subdivision Drainage Improvements project, located in Harris County Precinct 3, UPIN 26103MF3ZX01, MWDBE Contracted Goal: N/A, MWDBE Participation: N/A.
end
Background and Discussion:
The Golf Villas of Atascocita subdivision has experienced flooding during multiple storm events. The MUD has performed studies that outline the issues contributing to the drainage deficiencies within the subdivision.
Expected Impact:
To not partner with MUD 132 and continue to have high flood risk.
Alternative Options:
The County could elect to approve the requested task or choose to reject it. However, if not approved, the project will not be able to complete the scope of work.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): H6: Expand neighborhood drainage programs.
Economy Initiative (Goal 3): N/A
Health Initiative (...