Primary Department: Purchasing
Primary Department Head/Elected Official: Kimberly J. Williams, JD, Purchasing Agent
Secondary Department: County Engineer
Secondary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, County Engineer
Regular or Supplemental RCA: Regular RCA
Type of Request: Report
Project ID (if applicable): 20104MF1BY01
Vendor/Entity Legal Name (if applicable): N/A
MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a study report prepared by Civitas Engineering Group Inc., for West Riley Fuzzel Rd- from IH 45 to 200-ft West of West Hardy Rd - 2019, UPIN 20104MF1BY01, Precinct 3.
end
Background and Discussion:
This project consists of upgrading West Riley Fuzzel Rd from IH 45 to 200-ft West of West Hardy Rd, from existing 2-lane asphalt roadway to a 4-lane concrete curb and gutter boulevard, with 32' raised median, within a 100' ROW.
Expected Impact:
The project will improve the existent conditions of the subject road for the community in the specified area.
Alternative Options:
Without this project, this road segment will continue operating under the current conditions without the improved 4 lane configuration.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well-maintained infrastructure.
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): F1: Strengthen the County's commitment to Vision Zero principles and goals.
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal...