Legislation Details

File #: 26-0217    Version: 1 Name:
Type: Contract - Termination Status: Passed
File created: 12/22/2025 In control: Commissioners Court
On agenda: 1/8/2026 Final action: 1/8/2026
Title: Request for approval to terminate the agreement with GC Engineering, Inc for Professional Engineering Services in connection with Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019, Precinct 3.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom S. Ramsey, Commissioner

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Termination

Project ID (if applicable): 20104MF1BU01
Vendor/Entity Legal Name (if applicable): GC Engineering, Inc

MWBE Contracted Goal (if applicable): N/A
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to terminate the agreement with GC Engineering, Inc for Professional Engineering Services in connection with Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019, Precinct 3.
end

Background and Discussion:

Shaw Road Segment 2 - from south of Westlake Run Blvd to Boudreaux Rd - 2019. Project scope consists of Upgrade Shaw Rd from Northpointe Blvd. to Boudreaux Rd from partially half blvd, partially 2 lane asphalt to 4 lane concrete with curb and gutter and 32' median within 100' of ROW, study phase was completed.

Expected Impact:
The design and construction phase will be terminated.


Alternative Options:
An alternative is to move forward with the design and construction of the project.


County Strategic Plan Goal: N/A
County Strategic Plan Objective: N/A
Justice/Safety Initiative (Goal 1): N/A
Infrastructure Initiative (Goal 2): N/A
Economy Initiative (Goal 3): N/A
Health Initiative (Goal 4): N/A
Climate/Resilience Initiative (Goal 5): N/A
Housing Initiative (Goal 6): N/A

Additional notes related to the Strategic Plan:

Prior Court Action (if any):
Date
Agenda Item #
Action Taken
04/09...