Title: Request for approval to execute an agreement with Aviles Engineering Corporation in the amount of $97,253.25 for Professional Engineering Services regarding Construction Materials Testing and related services for Park and Road Improvements - Eisenhower Park - 2024, UPIN 25101MF3RN01, Precinct 1, MWBE Contracted Goal: 100%.
Attachments: 1. 26-0215-Consultant-UPIN 25101MF3RN01-Eisenhower Park-Aviles Engineering-P1-01082026
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV-SP, County Engineer

Secondary Department: Commissioner, Precinct 1
Secondary Department Head/Elected Official: Rodney Ellis

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Award

Project ID (if applicable): UPIN 25101MF3RN01
Vendor/Entity Legal Name (if applicable): Aviles Engineering Corporation

MWBE Contracted Goal (if applicable): 100%
MWBE Current Participation (if applicable): N/A
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with Aviles Engineering Corporation in the amount of $97,253.25 for Professional Engineering Services regarding Construction Materials Testing and related services for Park and Road Improvements - Eisenhower Park - 2024, UPIN 25101MF3RN01, Precinct 1, MWBE Contracted Goal: 100%.
end

Background and Discussion:

The intent of the project is to rebuild approximately 3 Miles of the roadway in a manner that enhances resilience against future extreme weather events. During the May 2024 Derecho event, Eisenhower Park experienced severe storms, straight-line winds, tornadoes, and flooding from Lake Houston Dam, San Jacinto River, and nearby rivers. Flood waters and high winds washed out roads, undermined culverts, and ditch slope, damaged/displaced gates, signs, and trees and vegetative debris.


Expected Impact:

This agreement will allow the firm to conduct field and laboratory testing on soil, concrete, asphalt and various other construction materials to ensure the material's compliance with Harris County Engineering Department's adopted standards and specifications as required by state law.

Alternative Options:

Construction material...