Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: Commissioner, Precinct 3
Secondary Department Head/Elected Official: Tom Ramsey
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Award
Project ID (if applicable): 15104M23NP03
Vendor/Entity Legal Name (if applicable): HR Green, Inc.
MWBE Contracted Goal (if applicable): 0%
MWBE Current Participation (if applicable):0%
Justification for 0% MWBE Participation Goal: N/A - Goal not applicable to request
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval to execute an agreement with HR Green, Inc., in the amount of $184,954.00 for Construction Phase Services in connection with Hufsmith-Kohrville Road Segment 3A project, UPIN 15104M23NP03, Precinct 3.
end
Background and Discussion:
This project will facilitate the construction upgrade on Hufsmith-Kohrville Rd from 700' north of Ezekiel Rd to approx. 400' north of Boudreaux Rd, from existing 2-lane asphalt roadway to a 4-lane concrete curb and gutter blvd, with 32' raised median, within a 100' ROW.
Expected Impact:
The project is expected to significantly enhance traffic flow, safety, and infrastructure resilience by providing a modern, well-planned boulevard with improved drainage and pedestrian facilities. It will reduce congestion, accommodate future growth, and integrate seamlessly with surrounding projects, contributing to the overall development and sustainability of the area.
Alternative Options:
If no action is taken, the prime consultant will not be able to proceed with Construction Phases Services, and this location will continue operating under existing conditions.
County Strategic Plan Goal: 2. Connect our community with safe, reliable, equitably distributed, and well...
Click here for full text