Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, Env. SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official:
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): 24104MF3A201
Vendor/Entity Legal Name (if applicable): AGHA ENGINEERING LLC
MWBE Contracted Goal (if applicable): 19.60%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of an amendment to an agreement with Agha Engineering LLC in the amount of $461,914.92 for Professional Engineering Services to provide improvements on Clay Road - Katy Hockley Rd to Katy Hockley Cutoff Rd - 2023, UPIN 24104MF3A201, Precinct 4, MWBE Contracted Goal: 19.60%, MWBE Current Participation: 100%.
end
Background and Discussion:
Harris County desires to amend the professional service agreement to extend the project limit around to 500 Ft east of Eula Morgan Rd due to continuous growth of the area, the new project limit is From 500 ft East of Eula Morgan Rd to 500 ft West of Katy Hockley Cut Off Road.
Expected Impact:
The project will upgrade and expand the capacity of the two-lane Asphalt roadway with 4 concrete lanes to handle the demands of the current and future traffic volumes. The improvement will alleviate congestion, reduce delays, and provide safe mobility for residents, pedestrians, and drivers in Northwest Katy; the project will provide safe crossings for students of Haskett Junior High School and Faldyn Elementary School.
Also upgrade the Road to concrete pavement will extend the pavement life and reduce the cost of road maintenance and rehabilitation.
Alternative Option...