Title: Request for approval of a change in contract with R Miranda Trucking and Construction LLC, in connection with Creel Country Estates Subdivision Drainage Improvements - 2018, with an addition in the amount of $2,157.00, Job No. 24/0406-01, UPIN 19102MF12T01, Precinct 2, MWBE Contracted Goal: 24.18%, MWBE Current Participation: 100%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0406, UPIN 19102MF12T01
Vendor/Entity Legal Name (if applicable): R Miranda Trucking and Construction LLC

MWBE Contracted Goal (if applicable): 24.18%
MWBE Current Participation (if applicable): 100%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with R Miranda Trucking and Construction LLC, in connection with Creel Country Estates Subdivision Drainage Improvements - 2018, with an addition in the amount of $2,157.00, Job No. 24/0406-01, UPIN 19102MF12T01, Precinct 2, MWBE Contracted Goal: 24.18%, MWBE Current Participation: 100%.
end

Background and Discussion:
Creel Country Estates is in the Spring Gully and Goose Creek watershed and in Precinct 2 in eastern Harris County. This site is generally bounded by E Wallisville Road to the north, residential development to the west and east, and O207-01-00 to the south. Creel Country Estates is in unshaded Zone X. Portions of the existing water and wastewater systems on Lyndale Dr, Bonneville Dr, and Cindyrella Dr need to be relocated due to utility conflicts. The proposed improvements are to regrade roadside ditches, upsize culverts to increase capacity, channel improvement, and to construct a detention basin for mitigation.

The change in contract includes the following:

? Added a new line item 91 for reimbursement to the contractor for an amount of $2,157.00 and zero days for CNP's installation and bracing of an existing pole ...