Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer
Secondary Department: N/A
Secondary Department Head/Elected Official: N/A
Regular or Supplemental RCA: Regular RCA
Type of Request: Contract - Amendment
Project ID (if applicable): Job No. 24/0368, UPIN 19101MF16P01
Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc.
MWBE Contracted Goal (if applicable): 29.57%
MWBE Current Participation (if applicable): 79.63%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above
Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item
Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with Ralston Acres Subdivision Drainage Improvements - 2018, adding 10 calendar days, with an addition in the amount of $51,969.50, Job No. 24/0368-1, UPIN 19101MF16P01, Precinct 1, MWBE Contracted Goal: 29.57%, MWBE Current Participation: 79.63%.
end
Background and Discussion:
This project is in Precinct 1 in Northeast Harris County. An engineering drainage system is currently in place; however, it is insufficient for current drainage needs. The proposed improvements are to upgrade the underground storm sewer system and connect to two detention basins that are also being constructed as part of the project.
The change in contract includes the following:
? Addition of quantities for existing line-item numbers 99, 100 and 101 for an increase in the amount of $51,969.50. The addition of 10 days to the contract.
The above additions and deductions result in a net change in the amount of $51,969.50 and 10 calendar days.
The County issued the Project's Notice to Proceed on 03/10/2025. Per Attachment M of the Contract, the work was to be completed within 600 days of the Notice to Proceed, or by ...
Click here for full text