Legislation Details

File #: 26-0193    Version: 1 Name:
Type: Contract - Amendment Status: Passed
File created: 12/22/2025 In control: Commissioners Court
On agenda: 1/8/2026 Final action: 1/8/2026
Title: Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Asphalt Package 2024-1, adding 11 calendar days, with a deduction in the amount of $480,928.97, Job No. 24/0374-1, UPIN 24208MF36G01, Precinct 3, MWBE Contracted Goal: 31.30%, MWBE Current Participation: 30.46%.
Primary Department: County Engineer
Primary Department Head/Elected Official: Milton Rahman, PhD, P.E., PMP, CFM, ENV SP, County Engineer

Secondary Department: N/A
Secondary Department Head/Elected Official: N/A

Regular or Supplemental RCA: Regular RCA

Type of Request: Contract - Amendment

Project ID (if applicable): Job No. 24/0374, UPIN 24208MF36G01
Vendor/Entity Legal Name (if applicable): Texas Materials Group, Inc.

MWBE Contracted Goal (if applicable): 31.30%
MWBE Current Participation (if applicable): 30.46%
Justification for 0% MWBE Participation Goal: N/A - Goal is not 0% and is listed above

Grant Indirect Costs Rate (if applicable): N/A
Justification for 0% Grant Indirect Costs Rate (if applicable): N/A - Not a grant item

Request Summary (Agenda Caption):
title
Request for approval of a change in contract with Texas Materials Group, Inc., in connection with final construction of Asphalt Package 2024-1, adding 11 calendar days, with a deduction in the amount of $480,928.97, Job No. 24/0374-1, UPIN 24208MF36G01, Precinct 3, MWBE Contracted Goal: 31.30%, MWBE Current Participation: 30.46%.
end

Background and Discussion:
The scope of work consists of, however, not limited for the rehabilitation of the Asphalt roadways to include 2.5 miles of Main Street (Crosby Lynchburg Road), within Harris County Precinct 3 Area.

Expected Impact
The Office of County Engineer (OCE) seeks approval of the following Proposed Change Orders (PCOs) with their corresponding approved RFIs:
* PCO #1 (RFI #8): Temporary work zone striping was required following milling operations to ensure the safety of the traveling public during construction. As this work was not included in the original contract, the Contractor submitted a proposal that was reviewed, approved, and concurred by the precinct. OCE seeks to compensate the Contractor accordingly.
* PCO #2 (RFI #13): Installation of 8" white solid striping, as required per plan sheets #25 and #26, did not have a correspo...

Click here for full text